Estimate
Activity Resources
Resources include
People, materials, equipment, facilities
Influence on the duration(important)
Availability of the resources
Types of resources
Sufficient quantities of resources for the
activity durations
Potential conflicts with other projects may
cause
Involve person with expertise in resource
estimate
Estimates influence costs
【•It is necessary to estimate the types and quantities of resources that will be required to perform each specific activity in a project.
【•It is necessary to estimate the types and quantities of resources that will be required to perform each specific activity in a project.
•Resources include people, materials, equipment,
facilities, and so forth.
•Having this information is essential in estimating how
long it will take to perform each activity and the project as a whole.
•A
number of factors influence the duration of an activity:
•Availability of the resources
•Types of resources
•Sufficient quantities of resources for the durations of
the activities
•Potential conflicts with other projects that may cause a
delay
•When
estimating the types and quantities of resources required for each specific
activity, it is valuable to involve a person who has expertise or experience
with the activity.
•Estimated
activity resources will also be used later for estimating activity costs and
determining the project budget.】
Estimate
Activity Durations
Duration must be the total elapsed time
Time for the work to be done plus any
associated waiting time
Builds buy-in from the person and generates
commitments
Avoids bias that may be introduced by
having one person estimate the durations for all of the activities
The designated individual uses experience
to estimate the durations
Historical data can be used as a guide
The estimated duration should be aggressive
yet realistic.
Durations should
not be too short to try to win the contract
Inflated
estimated durations is not good practice
Project manager
may not be able to negotiate shorter durations
Some activities
will take longer and others shorter durations than planned
As the project
progresses, level of confidence for accuracy increases
【•Once
the types and quantities of resources are estimated for each activity,
estimates can be made for how long it will take to perform the activities.
•The
estimated duration for each activity must be the total elapsed time—the time for the
work to be done plus any associated waiting time.
•The
figure above depicts the activity estimated duration for varnishing floors.
•It
is a good practice to have the person who will be responsible for performing a
specific activity estimate the duration for that activity.
•Builds buy-in from the person and generates commitments
•Avoids bias that may be introduced by having one person
estimate the durations for all of the activities
•It
is important to designate an experienced individual to estimate the durations
for all the activities for which the organization or subcontractor is
responsible in large projects.
•Historical
data can be used as a guide in estimating the durations of similar activities.
•Estimated
duration should be aggressive yet realistic.
•Inflating
estimated durations in anticipation of the project manager negotiating shorter
durations is not a good practice.
•Throughout
the performance of the project, some activities will take longer than their
estimated duration, others will take less time than estimated, and a very few
may conform to the estimated duration exactly.
•At
the beginning of the project, it may not be possible to estimate the durations
for all activities with a high level of confidence.
The project team can
progressively elaborate the estimated durations as more information is becomes
available to allow for more accurate estimated durations.】
Establish
Project Start and Finish Times
Define the overall window for project completion
May not want to commit to a specific date
Project not start until customer has approved the contract
Delay in contract signing may impact project start
Set finish time as number of days from
project start
【It is necessary to select an estimated start time and a required completion time for the overall project. This is important in order to establish a basis from which to calculate a schedule using the estimated durations for the activities.
•Define the overall window, or envelope, of time in which
the project must be completed.
•The contractor may
not want to commit to completing the project by a specific date until the
customer has approved the contract.
•A delay in signing
will likely impact the start date of the project.
•The finish time should be stated as a number of days
from the start of the project.】
Total
Slack
Sometimes called float
The difference between EF time of last
activity and the project required completion time
Negative slack (almost late)
Lack of slack over the entire project
Amount of time an activity must be accelerated
Positive slack (got plenty
of time)
Maximum amount of time that the activities on a particular path can
be delayed without jeopardizing on-time completion
【•Total slack is sometimes called float.
•It is the difference between EF time of last activity
and the project required completion time.
•Total
slack is calculated for each of the activities by finding the difference
between the EF time of the activity and the LF of the activity.
•You also look at the difference between the ES and LS of
the activity.
•Negative slack indicates:
•A lack of slack over the entire project
•The amount of time an activity must be accelerated to
complete the project by the required completion time
•Positive slack indicates the maximum amount of time that the
activities on a particular path can be delayed without jeopardizing completion
of the project by the required completion time.
•If the total slack is zero, the activities on the path
do not need to be accelerated, but cannot be delayed.】
Critical
Path (what must be accomplished)
Longest path in
the overall network diagram
Find which activities
have the least amount of slack
【•The critical path is this longest path in the overall network diagram.
•One way to determine which activities make up the critical path is to find which ones have the least amount of slack.】
Incorporate
Changes into Schedule
Changes may impact the schedule
Initiated by customer or project team
Result from
Early change may have less impact than
later change
Manage requested changes
Estimate impact
Obtain customer approval
Revise project plan, schedule, and costs
【Throughout a project, changes may occur that impact the schedule.
【Throughout a project, changes may occur that impact the schedule.
•Changes
might be initiated by the customer or the project team, or they might be the
result of an unanticipated occurrence.
•Changes
requested early in the project may have less of an impact on schedule and
budget than those requested later in the project.
•When
the customer requests a change, the contractor or project team should estimate
the impact on the project schedule and budget and then obtain customer approval
before proceeding.
•If the customer approves the proposed revisions to the
project schedule and budget, then any additional activities, revised estimated
durations, and revised estimated resources and associated costs should be
incorporated into the project schedule and budget.
•With
respect to the project schedule, changes can result in the addition or deletion
of activities, re-sequencing of activities, changes to estimated durations for
specific activities, or a new required completion time for the project.】
No comments:
Post a Comment